The Aerometro is a cable car between Guatemala City and Mixco, not a train; construction began January 5, 2026 (AGN). Works started on January 5, 2026 in zona 9, near Plaza España. AGN’s construction report describes it as high-capacity public transport that will carry up to 374,000 people a day, built with 100% private capital. As of October 21, 2026, none of the official-news items read gives a fare or an opening date. The route and hours below come from the regulation published in January 2021, so they describe the 2021 plan. For the State’s rail project, see Is there a train in Guatemala?; for transit you can use today, see Transmetro.

Quick summary

  • Status: construction began January 5, 2026 (AGN). No opening date published.
  • Fare: no official fare published.
  • Who is behind it: the Municipality of Guatemala. The builder named in the environmental licence is Cablevía de Guatemala, S.A. The President said in June 2026 that it is not a central-government project.
  • Capacity stated: up to 374,000 people a day between Guatemala City and Mixco; gondolas of up to 12 passengers (2021 regulation).
  • Hours in the 2021 regulation: around the clock in two shifts, 5:00 to 19:59 and 20:00 to 4:59.
  • Route in the 2021 plan: two lines from El Trébol, to zona 9 and to Molino de las Flores in Mixco, plus a transfer hub for buses to the west.

Timeline from official sources

DateWhat happenedSource
January 29, 2021The Reglamento del Sistema Aerometro Fase I is published in the official gazetteAGN; Diario de Centro America
August 23, 2024The Guatemala City council approves the concession, with three votes against: 25 years to the private sector, investment of Q1,216,448,000; approval of the intermunicipal agreement by Mixco’s council still pendingDiario de Centro America
August 2025The Ministry of Environment (MARN) grants the environmental permit after the project corrected technical weaknesses (area of influence, tree removal, wastewater treatment)AGN, January 6, 2026
January 5, 2026Construction starts on 10, 11, 12 and 14 calle, between 7 and 5 avenida, zona 9, near Plaza España, with temporary lane closuresAGN, January 5, 2026
June 5, 2026INGUAT says it has no link with the Municipality to extend the AeroMetro to La Antigua GuatemalaDiario de Centro America
June 23, 2026The President says the Aerometro is the Municipality’s project, not the central government’sAGN, June 23, 2026

The concession term differs between the two periods. The January 2021 AGN report said the project had been concessioned for 20 years; the council approval of August 2024 reported by Diario de Centro America was for 25 years.

The 2021 plan: lines, hub and hours

These details come from AGN’s and Diario de Centro America’s reports of January 29, 2021 on the Reglamento del Sistema Aerometro Fase I. The later items read do not publish an updated route.

ElementAs described in January 2021
Line IFrom the El Trébol bridge to 12 calle between 5a and 7a avenidas, zona 9, passing along bulevar Liberación
Line IIFrom El Trébol to Molino de las Flores, zona 2 of Mixco
Transfer hub“centra occidente”, in Mixco, near the closest Aerometro station, as the terminus for extraurbano buses travelling to the west of the country
Gondola capacityUp to 12 passengers
ServiceUninterrupted, in 2 shifts: day 5:00-19:59, night 20:00-4:59 the next day
Length and stations8.9 km and 10 stations (the Municipality’s description: AGN dates it to 2019; Diario de Centro America cites it undated)
ConnectionsWith the Transmetro trunk system and alternative transport such as bicycles (2019 description)

The regulation splits the concession into a construction stage (studies, design and engineering through to building and installation) and an operation stage (running the service, maintenance and improvements, then the end and settlement of the concession).

What the works involve

The January 2026 reports add these figures:

ItemFigureSource
People carriedUp to 374,000 a day between Guatemala City and MixcoAGN, January 5, 2026
Travel time on the routeCut by up to 75% (as stated in the report)AGN, January 5, 2026
JobsMore than 2,000 direct jobs during construction; about 500 direct and 2,500 indirect in operationAGN, January 5, 2026
InvestmentAround Q1,216 million, 100% private capitalAGN, January 5, 2026
Trees removed721MARN, via AGN, January 6, 2026
Trees to plantAt least 2,500, in three phases: 725 (510 at the zona 3 landfill and 215 along the side sections), then 932, then 912MARN, via AGN, January 6, 2026
Builder named in the licenceCablevía de Guatemala, S.A.MARN, via AGN, January 6, 2026

AGN’s construction report calls it the first urban mass public transport system by aerial cable in Central America.

What is not published

  • Fare: no official fare in any item read.
  • Opening date: none.
  • Current station names: the items read give no station list; the 2019 figure is 10 stations.
  • Timetable after 2021: the two-shift hours come from the 2021 regulation only.

For getting around the city today, see transport in Guatemala.